
K C E S T R U C T U R A L E N G I N E E R S , P. C.
· 1818 JEFFERSON PLACE, N.W. · WASHINGTON, D.C. 20036 ·
KCE Junior College
To send your questions to Professor Kilsheimer, send an e-mail to kce@kcestructural.com with "KCE Junior College" as the subject.
| Date posted |
Questions and Answers |
|
11/02/04
|
Some questions on certain KCE Specifications-- Section
2151 Excavation,
Sheeting, Shoring, Underpinning, and Dewatering 1.2B What is unclassified excavation? No
extra $, rock or not 1.2F What is a 3” minimum concrete work
mat?
To
stop rock from fluffing
up overnight 1.3O What are inclinometer casings?
Device we shove monitor down into
to check for ground moisture 1.3P What is a work slab?
See 1.2F 2.1A What does plasticity measure in soil?
Flow, if liquid 2.3A What is dywidag threaded bar?
1-¼” diameter high strength
bar 2.3A Need general explanation regarding footing
tie downs.
To stop building from falling
over 3.1A Need general definitions of sheeting shoring,
underpinning, bracing and sheet piling.
See
3.1.F 3.1B How is movement detection generally
accomplished? See 1.3O &
sheeting & shoring, but generally it is detected with bar graph
& reflector targets placed on soldier beam and read by instrument. 3.1F Need general definition of rakers,
tiebacks and walers.
Rakers are diagonal steel
members, kicked back into excavation to hold up waler soldier beams
(removed); Tiebacks are drilled rods under adjacent property to hold up
walers, horizontal members which hold up soldier beams – stressed and
left in place; Soldier beams are vertical steel members, in this case
drilled into ground and abandoned; Lagging is 3” / 4” boards between
soldier beams 3.7B Why do you need to chlorinate your wells once
a month?
To keep filters clean Section
3300 Poured
in Place Concrete 1.3B4 What is visqueen vapor barrier?
Plastic sheet 1.3B9 What are the concrete additives hydrocide or pozzilith?
Water-tightness 1.3B11 What is inertia or house keep slabs?
Stops vibration from being felt
in office space due to vibration 1.3B12 What is admixture?
Additive to concrete mix 1.3B13 What are galvanized dove tail slots at masonry and galvanized
reglets at flashing?
To hold water-tightness elements
into concrete 1.3B14 What are boxes for holes in concrete?
M.E.P. (plywood, removed) 1.3B16 What is a concrete garage interceptor?
Takes garage water & takes
out contaminent 1.3B24 What is crystalline waterproofing?
Hard finish, troweled on
waterproofing 1.3B25 What is RXPlus floor/foundation walls and intersections?
Black caulk for water finish 1.3B29 What is lean concrete?
2000 psi (little cement) 1.3B38 What is lagging at perimeter of building?
See 3.1F above. 1.3D7 What are corner guards for the parking garage?
Angles to stop cars from damaging
concrete 1.6 That’s a lot of test.
How are we organizing all that information?
The
tests described are required to ensure proper quality control on the
job, and to meet all Code and
1.6
TESTS
A.
Concrete: The Contractor shall name his source of supply for
concrete materials, and shall submit to the Structural Engineer for
approval, copies of the mix designs he proposes to use, certified and
sealed by a Professional Structural Engineer registered in the
1.
Test cement in accordance with the ASTM physical test
requirements. One test shall be made for each carload of cement.
2.
Make Quality Test of materials including reinforcing steel, but
Certified mill test reports will be acceptable.
3.
Concrete test cylinders shall be taken, cured and tested in
accordance with the ASTM Specifications.
Concrete cylinders shall be paid for by the Owner.
Each cylinder shall be clearly marked to permit easy
identification. Sets of test cylinders shall be taken and tested as
follows:
a.
It shall be the responsibility of the Concrete Subcontractor to
notify the testing laboratory of the concrete pouring schedule with a
minimum of 24 hours notice in order that the sample cylinders may be
taken. Provide minimum of 24 hours notice to testing laboratory.
b.
Take a set of cylinders for each 100 cubic yards of concrete for
each day's pour and for each class of concrete.
These cylinders shall be made at the point of discharge from the
truck and shall be made in accordance with the latest edition of ASTM
C_172 and shall be laboratory cured and tested in accordance with the
latest edition of ASTM C_31 and ASTM C_39. The
cylinders shall be made and tested in accordance with the following
schedule:
(1)
Columns (with f'c #
5000 psi), walls, beams, framed slabs:
Each set shall consist of eight (8) cylinders, 2 field cured and
2 lab cured cylinders to be tested at 7 days, and 2 field cured and 2
lab cured cylinders to be tested at 28 days.
(2)
Footings, slabs on grade: Each
set shall consist of four (4) cylinders, 2 lab cured cylinders to be
tested at 7 days, and 2 lab cured cylinders to be tests at 28 days.
(3)
Columns / slabs with f'c $
5000 psi: Each set shall
consist of twelve (12) cylinders, 2 field cured and 2 lab cured
cylinders to be tested at 7 days, and 2 field cured and 2 lab cured
cylinders to be tested at 28 days, plus 2 lab cured cylinders to be
tested at 84 days and 2 lab cured cylinders to be tested at 112 days.
c.
Additional tests as directed by the Architect's Structural
Engineer.
d.
Take additional cylinders as required for stripping decisions;
cost to be born by the Contractor.
4.
Submit test reports, within 7 days of the test,
as follows:
a.
One each directly to the Architect, Owner's Representative,
governmental officials and the Structural Engineer.
b.
If the test cylinders indicate that the concrete does not meet
the requirements of the project, the Structural Engineer may require
additional testing to be done. The
expense of the additional tests, in any case, shall be borne by the
Contractor. 2.1I What are water stops?
See 1.3B25 3.1 Concrete Proportions,
Strengths, and Mixes B1
What are concrete slumps? Amount concrete slumps … once test
cone in which concrete is place is removed – this helps measure
water content of concrete 3.1D Why do you recommend all concrete being
machine mixed?
Because
there is no room for batch plant on site 3.1I What is retempering of concrete?
Fucking with it after truck shows
up 3.3
Forms, Shoring and
Tolerance C What do you
mean every unstressed floor shall be reshored by two fully stressed
floors?
So it won’t collapse 3.4
Reinforcing Steel D What are temperature
bars?
Bars place where there are no
bars in one-way slabs to control cracking F What are high
chairs, beam bolsters, and stirrups? High chairs hold
up top reinforcing; beam bolsters hold up beam reinforcing, and stirrups
are part of shear design 3.5
Placing Concrete G
What do you mean additional concrete shall be in each bay on
metal deck equal to the beam camber amount?
So no extra $ is charged when
formwork deflects, and more than “neat” volume is poured, until
concrete hardens Section
3315 Post
Tensioning 1.2A
What is full tendon bonded post tensioning?
Grout pumped into cable tendons
are in & make anchorage bond continuous 1.3D
What is bursting steel?
Steel at trumpets @ ends to stop
concrete from blowing up 1.3E
What are additional cylinders?
Additional test 6”x12”
cylinders 1.3F
What are grouting tendons?
See 1.2A above 1.8
Shop Drawings C
What are jack clearances, stressing sequence, initial tensioning
forces, gauge pressers, and tendon elongation?
Braided wires ± 1/” diameter
are rolled out in plastic sheets on formwork help up by slab bolster and
high chairs and placed with a parabolic type profile to specified
dimenions we design. At the
ends of beams the wires flare out in both directions to cover
essentially the whole end of the beam in a pepper box fashion.
These are dead end enclosed on the street side and steel trumpet
and wedges on the stressing end. Once
the concrete reaches a certain strength, before the formwork is removed,
the tendons are pulled by hydraulic jack, one at a time, until a
predetermined lengthening is gained (elongation based on wire strength
and force we want in cable. The
wedges are driven into place, and the tails of the wires left hanging
out. Elongation is observed
by our inspector and reported to our office.
Once we review and assure ourselves we have the force we want,
and we have the concrete breaks to verify the concrete strength we want,
we write burn off letter and stripping letter allowing the tendon tails
to be burned off and the slabs stripped.
Once burned off there is no real way to get more force in member.
D
What is a friction wobble coefficient?
Depends on trumpet and sheathing
dimensions 2.1
Materials B4 What are oil tempered
wires?
Rubbed with oil for corrosion
protection `` |
|
11/03/04
|
More Questions & Answers, on a variety of topics: 1Q. Curing the design phase, how is a structure itself determined (steel vs. concrete)? Eliminating the fact that concrete is good for hotels for painted ceilings and the fact that concrete is good for downtown D.C. buildings due to the overall height requirement, what else dictates steel vs. concrete? 1A.
Structural steel vs. concrete is usually based on:
spans, building height, foundation considerations, lead time
(foundation hole or not), load carrying capacity, future use
considerations, access restrictions. 2Q. Why do so many projects follow this same pattern: Something appears wrong with the concrete mix. Lots of repetitive failures on multiple cores. We call a big meeting. Testing agency blames the concrete supplier, supplier blames the agency. Owner yells at structural. Miraculously, the problem is solved and far fewer sub-standard breaks follow. Here is the bottom line, if it is so easy to get the “mix” right, why not simply do it right from the start? 2A.
The issue is money. Owners
don’t want to spend a lot for testing … Contractors want to use
minimum cement in concrete. Most
structural engineers don’t specify minimum material in mixes (just
strength). If they required
minimum mixes fewer issues would arise, but jobs would cost more. 3Q. What is the difference between a “restrained” and “unrestrained” structure, and how is the structure determined to be either? 3A.
This applies to a steel building and its method of design.
A composite steel structure with moment connections would be
restrained. A steel
warehouse would be unrestrained. The
restrained/unrestrained issue usually comes up regarding fireproofing,
which is different for each design method. 4Q. Why is there a W8x10 across a single elevator shaft? 4A. Counterweights on side (on single), or
at end for multiple elevators, and to support guide rails for a rear
door elevator to provide space for counter-weights and support rails.
Once could call for a compound bracket that would do both. 5Q. What does it mean to be “spirally reinforced”? 5A. For columns to have slinky-type
continuous ties to increase stiffness ±10% 6Q. What is an upset beam? 6A. Poured flush with slab and balance
above slab. 7Q. When are buildings built on geo piers vs. caissons or just slab on grade? 7A. Geo piers, caissons, piles, spread
footings or mat are all foundation types.
The slab on grade is just a cover over the earth to walk on. 8Q. Why do you have a removal slab over mechanical room? 8A. To allow equipment that won’t fit
down the access (or up the access for removal) to be installed or
removed. 9Q. In a flat slab structure, what does it mean to say: to be top and bottom mat lapped alternating at mid-bay of span? 9A. Instead of arranging reinforcing per
typical flat slab details, bars are continuous with alternate splice
locations to resist progressive collapse. 10Q. Pull pockets & beam project in post-tensioning – what is the beam projection? What if you put a column at the end of the PT beams; do you still need pull pockets? Are there holes in the slab for pulling pockets? How big is a pull pocket? 10A. Beam projection is same as pull pocket.
You still need pull pockets if you put column at the end of the
PT beams. Yes, there are
holes in the slab for pulling pockets.
A pull pocket is ±12” 11Q&A. Vocabulary Questions a.
soldier beam – vertical members driven / drilled into the ground to hold out earth and
support lagging b.
raker braced – using rakers (diagonal steel members to concrete heel blocks cast in
excavation) to temporarily hold up S.D.
c.
walers – temporary steel members across the face of S.D. d.
garage interceptor – plumbing device to run garage drainage
water through to remove oil before it goes into sewer
e.
dwi-dag bars – high strength 1-1/2” deformed bars
f.
RD, FD sweeps – roof drain, floor drain pipes g.
cambered slabs – poured like a tent, with the center of each
bay up; for steel, a member set up in the center (fabricated that way)
h.
ceiling plenum – space between bottom of structure and
suspended ceiling 12Q&A.. Please explain what the following measure and how they differ. a.
Pachometer (profometer) – a magnetic device that you rub
across concrete surfaces to locate metallic elements & their
approximate size & depth, omni-directional
b.
Ferroscan – similar to pachometer, but better & more
expensive
c.
X-rays – just as with your bones, looking for elements
embedded in concrete
d.
GPR – Ground penetrating radar, used to locate voids in
concrete, earth, etc.
e.
Soundings – resonance device looking for voids, rock depth,
etc. 13Q. How do you know which method to use & when? 13A. Cost and/or type of material being looked at, eg.
post-tensioning 14Q&A. What are the various methods of testing for concrete strength & how do you know when to use which method? a. Cylinder – sample taken during concrete pouring process, cured & broken in laboratory to demonstrate strength; used during job b.
Schmidt Hammer – calibrated device bouncing metal ball off
concrete to get an approximate strength reading; 1st shot @
guessing strength c.
d. Cores – samples drilled out of concrete; method per ACI for determining strength of poured concrete |